Water connections

Building or converting a property? Let’s get you connected to our water main.

Yorkshire Water colleagues

For developments where no new road is being built, we’ll provide a connection from our existing network that perfectly suits your needs and supplies safe, great-tasting drinking water all year round. You can find the applications forms in the 'Get connected' section, below.

Once you've applied and made the applicable payment, we’ll do a survey to check how we can best deliver your water and get back to you with a quote for the connection work within 28 days. Our delivery team handles the connection, which normally takes no more than 21 days (but do bear in mind, if the work is on a busy road, it may take up to three months as we’ll need to notify the local council).

 

Building a new road?

You may need to apply for a new main.

 

Who’s responsible for your pipes?

Learn more about pipework responsibility

 

Calculate your estimate

Get an estimate for a new or replacement water connection:

  • it's free
  • it takes less than 3 minutes
  • you can calculate an estimate for up to three household connections
  • you'll get a rough idea of the costs so you can decide what to do next.

Get connected

Before you apply, take a look at our guide to water connections to understand each stage of the process:

Your guide to water connections

You can read this document in your browser or download it.

Please fill out an application form for water connections using the link below:

Application for water connections

You can download and print this PDF or fill it out using Adobe Acrobat Reader. Alternatively, sign up to our online portal to apply online.

If you’d like to stay up to date on how your application is going, enter your application reference into our application tracker using the link below:

Track your application

Enter your application case reference number to get updates.

6 simple steps to a new connection 

Here’s what you need to do – and what we’ll do – at each stage of your journey.

1

You apply and pay your application fee

Fill out a water connections application form and pay the application fee. We’ll get back to you within 5 days to let you know we’ve got everything or if we’re missing any details.

2

We send you a quote

We’ll do a site survey and send you a quote and a connection plan within 28 days of receiving your completed application.

3

You pay your quote

If you’re happy to move ahead, you’ll need to pay your quote and book in the connection (see step 5) within 6 months of receiving the quote.

4

You lay your pipework

Arrange to lay your private supply pipe up to the property boundary ready for us to connect to. We recommend using a qualified contractor to make sure this is done right.

5

You book in your connection

Complete and return the connection checklist we sent you with your quote to confirm you’re ready for the connection. If it’s for a new property, you’ll also need to send us a letter from the local council confirming the address.

6

We make the connection and install your meter

We’ll come to carry out the connection and install your water meter within 21 days of receiving your completed checklist.

How do I get my private water pipe installed?

Before we can get you connected to our water network, you’ll need to arrange the installation of the private water supply pipe within your property boundary. While you can install private pipework yourself, we recommend using a WaterSafe-approved plumber to make sure it’s done right.

Check out our handy video guide on how to go about getting your private pipe installed:

Additional documents

Water regulations enforcement policy

You can download and print this PDF or fill it out using Adobe Acrobat Reader.

Notification of plumbing works (Regulation 5)

You can download and print this PDF or fill it out using Adobe Acrobat Reader.

Backflow protection policies

You can download and print this PDF or fill it out using Adobe Acrobat Reader.

Meter location policy

Learn more about meter locations here, or have a look at our meter location policy for more detail.

Water UK contaminated land assessment guidance

Learn more about contamination assessment here.

Re-quote request form

You can download and print this PDF or fill it out using Adobe Acrobat Reader.